The lighting upgrade at Oxenham Park is progressing well!
Here’s a summary of the key points:
Current Status: The lighting upgrade at Oxenham Park is nearing completion.
Work Schedule:
20 & 21 August: Final two footings will be drilled on Ken Mackay Oval.
27 & 28 August: All four purpose-built towers will be assembled and stood on-site.
Completion: This will conclude all major construction, leaving the ovals free of significant construction activities.
Project Goal: The lighting upgrade is designed to enhance nighttime cricket play while minimising the impact on nearby residents.